In the home construction and renovation trades, specifically electrical as well as electrical rough-in refers to an initial stage following the installation of the essential services that are in place but not yet completed. In particular, rough-in plumbing refers to the first step in setting up water lines, drain lines, vents, and pipeline connections. After this infrastructure is installed and endorsed by a construction inspector, plumbing experts can proceed to the final plumbing stage.

Although rough-in plumbing refers to a process commonly used by professionals in plumbing, however, it is also used in building layouts and plans. Suppose you’re thinking of buying an apartment, and notice that an unfinished section in your basement is listed as having rough-in plumbing. In that case, it means that drain, water, and vent lines have been put in place to serve as bathrooms or kitchens in the basement. Learn more about rough-in plumbing and the best way to utilize rough-in plumbing.

What Rough-in Plumbing Is

Plumbing rough-in is the process of constructing vents, sewage systems, connections, and water lines. In a broad sense, the term “rough-in” can be a reference to the phase of construction following the initial framing has been completed and the first services, like the wiring and pipes, have been put in place; however, their final points, such as fixtures or outlets, were not installed.

The excavation and installation of underground pipes connecting the utilities to the structure are completed in the rough-in stage. The lines are routed through wall cavities, vent stacks are connected through the roof, and drain pipelines are joined to the system for sewer or septic system. The water lines are then joined to the central valve for water supply, and pipeline connections are created. After the rough-in stage, it is time to begin the final plumbing phase.

Rough-in vs. Finish Plumbing

The first step of putting in plumbing infrastructure for constructing a new home is called rough-in plumbing. Finishing plumbing is the following stage in the process. It is where the plumber will begin setting up faucets and drains under the sink assemblies, water system valves, and various other fixtures.

Plumbing rough-in is usually performed by a licensed plumber with the experience and training. At this point in the construction process, the plumber is responsible for digging the yard to connect underground water and drain lines to the utilities to the main structure. The plumber will also make holes for drain lines, water lines, vent stacks, and drain lines when necessary throughout the house. After drilling holes, the plumber will run the water pipes, drain lines, and vent stacks into the wall cavity, constructing pipeline connections as needed.

Final plumbing occurs following the finalization of the rough-in plumbing stage. A few experienced DIYers might be able to manage the final plumbing phase; however, for the most effective outcomes, it is recommended to work with a professional plumber. In this project stage, all caps placed on the drain or pipes for water supplies are removed, and fittings for plumbing are completed. The plumber will install under-sink drain assemblies, set up water system valves, and examine the connections to ensure no leaks.

How to Do Rough-in Plumbing

In the event of completing plumbing rough-in plumbing by yourself to build a new home is not advised in the absence of professional experience and is current in terms of building codes and inspection specifications. If you’re installing plumbing rough-ins for a kitchen, bathroom, or laundry room within an existing house, there is a chance that you can do a little bit of the task based on your experience, knowledge, and skills. Be aware that the work you are doing is examined before moving on to the final plumbing.

When it comes to rough-in plumbing, there are many essential aspects to consider. Gravity is the most crucial element in any drainage system. Therefore, drain lines should be placed in as to angle downwards. Do not use long horizontal drain lines in any way. In addition, you must ensure that the wastewater system is adequately vented to prevent any future problems with your home’s plumbing system.

Excavate and Lay Main Water and Drain Lines

The rough-in plumbing process typically begins with excavating the areas needed to connect the utilities’ drain and water lines to the main building. Once the site is excavated, you can either finish the connections on your own if you have the skills or engage an experienced plumber to run your main water lines as well as the primary drain line through the utilities up to your building.

Measure and Drill Tub and Toilet Drains

Once the main water and drain lines have been installed, you can concentrate on the bathroom. Level each tub to determine where the drain should go. Then take the tub off and create a hole to drain. Make sure that you’re not placed over a floor joist when you begin drilling.

Once you’ve made holes, you can reposition the tub and secure it with two-inch screws. While within the bathroom, take measurements and mark the location of the toilet. It must be positioned approximately 13 inches from the wall to the back and, at a minimum, 15 inches away from the tub. Utilize a hole-saw to create a hole for the drain of the toilet.

Drill Holes for Drainage and Venting

The next step of the procedure is to use the hole saw to make holes for drainage lines and venting stacks into holes in the walls. Consider gravity when you place the drain lines to ensure you don’t accidentally create long horizontal drain lines.

When gluing drain fittings, use the application brush to paint the pipe evenly and the outside of the fitting. The line should be pushed into the fitting and then moved left and right so there aren’t any bare areas inside the joint. Clean any glue that is left before its setting.

Vent stacks must be able to extend from the basement up to every floor until the roof. This means you’ll have to climb into an attic area to install the proper vents and connect them to the outside.

Drill Holes and Run Water Lines

Once you have the vent and drain lines installed, you can put in pipes for water. It is generally best to install 3/4-inch pipes close to the point where they must be in the kitchen, bathroom, or other appliances that use water, like fridges or washing machine dishwashers. Reduce the 3/4-inch line of water to one-half inch for each device.

Ideally, the 1/2-inch pipe should be as straight and short as possible, it is also advisable to consider drilling holes outside your home to accommodate hose lines or bibs. Depending on where you live, it might be beneficial to incline the lines of hose bibs upwards to prevent freezing in winter.